Cutting costs with shorter frack stages

On a Delaware pad in October, we went from 250 ft to 200 ft stages and dropped cluster count from 6 to 5; treating pressure eased about 700 psi, completion time fell about 5 hours per well, and we avoided a day of rig standby — about $85k saved. Anyone seeing similar results on slickwater jobs, and does any EUR impact erase the cost win?

‌⁠‍⁠​‍​‍‌⁠‌​​‍​‍​⁠‍‍​‍​‍‌‍‌‍‌⁠​‍‌‍​‌‌‍​⁠‌‍‍⁠‌‍‍‌‌‍⁠‍‌‍‌⁠​‍​‍​‍⁠​​‍​‍‌‍‍⁠​‍​‍​⁠‍‍​‍​‍‌‍⁠‍‌‍‌‌‌⁠‌⁠‌‌⁠⁠‌⁠‌​‌‍⁠⁠‌⁠​​‌‍‍‌‌‍​⁠​‍​‍​‍⁠​​‍​‍‌‍‍‌‌‍‌​​‍​‍​⁠‍‍​‍​‍‌‍⁠‍‌‍‌‌‌⁠‌⁠​‍​‍​‍⁠​​‍​‍‌‍‌​​‍​‍​⁠‍‍​‍​‍​⁠​‍​⁠​​​⁠​‍​⁠‌‍​⁠​​​⁠​‌​⁠​‍​⁠‍​​‍​‍​‍⁠​​‍​‍‌‍‍​​‍​‍​⁠‍‍​‍​‍‌​‌​‌‍‌‌‌⁠​‍‌‌​⁠‌​‍‍‌‍⁠‍​⁠​⁠‌⁠‌‌‌‍‌‌‌‌‍‌‌⁠​‍​⁠‌‍​⁠‍​‌⁠‍​‌‌‌‌‌⁠​⁠​‍​‍‌⁠⁠‌